South African renewable energy developers cannot lead bids in a new Eskom Green tender because of strict entry rules, MyBroadband reported. The tender is for partners to build up to 6 GW of solar, wind and battery power.
Eskom issued the request for qualification on 2 October 2026. It wants a five-year panel of partners for Eskom Green, its new renewable energy company. Responses close on 12 January 2027.
Eskom will put in at least 2 GW of solar PV and 1 GW of battery storage on its own land and sites. The partners will help develop, finance and build the projects.
The tender has four pass or fail rules. A company that fails any one of them is disqualified. The lead bidder, or a parent company that controls it, must meet the first two rules on its own.
One rule requires a single solar or wind project of at least 240 MW that is already running. Projects at financial close or under construction do not count. Smaller phases at the same site cannot be added together.
In its own published answers to questions, Eskom recorded a point made by a bidder. Only one running solar or wind project of that size exists in South Africa.
That project is the 240 MW Mooi Plaats solar plant near Noupoort, which started running in March 2026. It belongs to Envusa Energy, a joint venture of Anglo American and France’s EDF. Black-owned Pele Green Energy holds 20%.
Even Envusa fails on its local assets alone, MyBroadband reported. Its Koruson 2 cluster totals 520 MW, short of the 800 MW portfolio test.
The report said local firms are held back by how the state bought power in the past. The REIPPPP programme usually capped projects at 75 MW for solar and 140 MW for wind. Bid Window 5, awarded in 2021, still used those sizes.
Larger local projects, such as Red Rocket’s Overberg, NOA’s Khauta South and Mulilo’s Beaufort West, will pass 240 MW. But they will only start running some months after the closing date.
When asked whether the rule was meant to keep South African companies from leading bids, Eskom said no. But it turned down every proposed change, including counting projects at financial close. It also declined to create a separate category for local developers.
Experience anywhere in the world counts, and no South African experience is needed to pass the first stage. The rules were later changed to accept offshore wind projects and the track record of fund managers.
MyBroadband named EDF, Copenhagen Infrastructure Partners, Scatec, Engie, ACWA Power, Masdar and TotalEnergies as likely lead bidders. Copenhagen Infrastructure Partners has owned most of Mulilo since 2023, so it could bid with Mulilo in its group.
SOLA, Red Rocket, NOA and Pele have no foreign parent company. They would need a large international firm willing to take them on as partners.
“SA Inc should have a primary seat at the table at this critical juncture,” said Manufacturing Circle executive director Philippa Rodseth. She said this should include local developers, contractors and manufacturers.
The report compared the tender to the Independent Transmission Projects programme. In July 2025, the Department of Electricity and Energy asked for bids on about 1,064 km of new power lines worth roughly R17-billion.
On 15 December 2025, Minister Kgosientsho Ramokgopa named seven pre-qualified bidders from 17 who applied. All were led by international companies, and local firms were left to bid for subcontracts.
Questions about the Eskom Green tender close on 30 November 2026. Final responses are due on 12 January 2027.
Source: this article is based on reporting by MyBroadband. Image: MyBroadband. Written with the help of AI and published by the Tzaneen Voice Business desk. See our Editorial Standards.
Anelisa Nkuna covers business and money news for Tzaneen Voice. Anelisa reports on the rand, fuel prices, interest rates, jobs, Eskom, Transnet, farming and company results. The aim is simple: explain what the numbers mean for household budgets, small businesses and workers in South Africa.