AI Data Centres in South Africa Bring Few Permanent Jobs and Raise Water and Land Concerns

By

November 24, 2026

The growth of AI data centres in South Africa is creating far fewer permanent jobs than building work, and is raising questions about water and land, IOL reported.

Equinix said its centre outside Johannesburg employed around 750 people while it was being built. The site now has only 26 permanent staff, according to the company.

Dominic Cull, a regulatory advisor for the Internet Service Providers’ Association (ISPA), backed a probe into the issue. “Let’s establish the facts and use them to figure out an evidence-based balance between socioeconomic development and observing fundamental rights, and growth and the economy,” he said.

The SA Human Rights Commission called for public submissions in May 2026. It wants views on the human rights effects of data centres and digital infrastructure in the country.

After his working visit to Silicon Valley, President Cyril Ramaphosa said South Africa is becoming “Africa’s digital infrastructure hub”. He said the country has more than 60 working data centres. Planned projects could more than double that capacity, he said.

Operators such as Teraco, Equinix and Microsoft are growing their large facilities. The demand comes from cloud use, businesses going digital and the global race for AI computing power.

Estimates of what AI could add to the economy differ widely. PwC gave a careful estimate of a 1.2% total rise in GDP over ten years. The Presidency put the figure at R1 trillion to R1.4 trillion, with hundreds of thousands of digital jobs by the end of the decade.

Building a data centre creates hundreds to a few thousand short term jobs for electricians, cooling experts and security staff. According to the Hamm Institute, a 170 MW site like the one planned near Cape Town would create only a few dozen lasting tech jobs.

A bigger campus of about 400 MW is planned in eThekwini near the Lovu River. Its backers estimate 500 permanent jobs and 5,000 construction jobs for the project, which could cost between $3 billion and $10 billion. The eThekwini Municipality said the council signed an early Memorandum of Agreement but gave no more details.

Water use is the biggest point of dispute. The Housing Assembly, Foxglove and the Legal Resources Centre estimate that some planned Cape Town sites could use as much water as more than 18,000 households in a year if older cooling methods are used.

In Durban, DA councillor Andre Beetge questioned the eThekwini plan. “Why is there no regulatory framework referenced in this proposal?” he told iAfrica.

Operators said newer closed loop and air cooled systems use very little water. Teraco reported figures of about 0.03 litres per kilowatt hour. The company said local conditions are different from dry markets in the United States.

ISPA said data centres should follow the same environmental and planning rules as other infrastructure projects.

A UNESCO report on South Africa’s AI readiness found that land for AI ties in with the country’s unfinished land redistribution work. Large campuses need well located land in or near cities. This land is also needed for housing, where waiting lists are long.

Solar farms built to power data centres can also take up farm land, the report said.

Rezoning for data centres takes a long time. There is no rule forcing operators to publicly share their water, power and community benefit plans. Civil society groups have lodged appeals and called for a national inquiry.

Source: this article is based on reporting by IOL Technology. Image: IOL Technology. Written with the help of AI and published by the Tzaneen Voice Technology desk. See our Editorial Standards.