PPC Says Its R3.1 Billion Western Cape Cement Plant Is on Track for Early 2027

By

November 24, 2026

Cement maker PPC said its new R3.1 billion cement plant at Riebeeck West in the Western Cape is on schedule and within budget.

The plant is called Riebeeck West Kiln 3, or RK3. It will be able to make 1.5 million tonnes of cement a year once it runs.

“The new RK3 plant remains on track for completion in the final quarter of FY27 and within the Board-approved budget,” the company said.

PPC shared the update in its interim results for the six months that ended on 30 September 2026. The results were released on 16 November. The company expects building work to be done between January and March 2027.

PPC said it had spent R2.212 billion on the project so far. This includes prepayments and foreign exchange losses. Of that amount, R1.282 billion was spent during the six months under review.

According to PPC, design work on RK3 was 99.8% complete and buying of equipment and materials had reached 98.8%. Civil works were 85.3% done.

Structural, mechanical and electrical work stood at 40%. The company said building of the Eskom substation and switching station was 90% complete.

The plant will have its own solar power. PPC said it will also use technology to save energy, burn less coal and cut emissions for each tonne of cement it makes.

These changes could lower PPC’s running costs. Energy and transport are large costs for cement makers. IOL Business Report said any benefit to builders and buyers through better cement prices will depend on market conditions and PPC’s own pricing choices.

PPC chief executive Matias Cardarelli said the plant is part of the company’s longer plan to make its finances and operations stronger. In its results, PPC said it was “investing in tomorrow’s competitiveness” while keeping its balance sheet strong.

The new plant comes at a hard time for the local cement industry. Demand is weak, price competition is fierce and imported cement is putting pressure on local makers.

PPC’s results showed that cement sales volumes in South Africa and Botswana fell by 7.9% compared with the same period last year. South African volumes dropped by 5.8%, while Botswana saw a fall of 37.7%.

Revenue from the South African and Botswana business fell by 2% to R3.185 billion. PPC said better pricing and a better product mix helped make up for some of the lower sales.

The company blamed weak demand and heavy price cuts by some rivals trying to sell more cement. PPC said it would rather focus on sales that add value than chase volume by cutting prices.

PPC also said its anti-dumping complaint about cement imports from Mozambique and Vietnam was moving forward. The case is before the International Trade Administration Commission of South Africa.

The company said a good result would help bring back fair competition and support local factories. PPC said restoring “a level playing field” was important for local cement production to survive.

Sinoma Overseas Development Company is the engineering, procurement and construction contractor on the project. PPC said RK3 had reached about 1.7 million work hours without a lost-time injury by early October 2026.

Source: this article is based on reporting by IOL Business Report. Image: IOL Business Report. Written with the help of AI and published by the Tzaneen Voice Business desk. See our Editorial Standards.