Eskom said South Africa has now gone more than 550 days in a row without load shedding, a run that started in May 2025.
The power utility also said its load reduction footprint has shrunk by 94%. Only 102 551 customers are still affected, down from about 1.69 million.
“Eskom currently has approximately 4 274MW of surplus capacity above current demand requirements, strengthening system resilience and creating headroom to support additional electricity demand,” the utility said in a statement, according to SAnews.
Eskom said its Energy Availability Factor for the year so far has improved by about 12.57%, reaching 68.13%. It said average unplanned outages have dropped by 7 090MW.
The utility said the spare power could support energy-heavy industries, new investment and more electricity exports. It said this could help South Africa become a regional electricity hub.
Eskom said the better performance has cut its use of diesel-fired Open-Cycle Gas Turbines. Its diesel spending for the financial year so far stands at R1.284 billion.
That is R4.796 billion less than the R6.080 billion it spent during the same period last year, Eskom said.
The utility said the expected effects of El Niño are not seen as a risk to electricity supply or grid stability. It said its Generation Recovery Plan has made the power stations stronger.
Eskom said hotter weather could cause power losses at some coal-fired units. It said drought could also push up demand for exports from neighbouring countries that rely on hydro power.
“The improved generation performance provides sufficient operational headroom to absorb approximately 2 000MW of potential heat-related generation losses, while maintaining about 5 000MW of surplus capacity during peak periods,” Eskom said.
The utility said its pollution targets were also met. It said particulate emissions up to the end of October 2026 stayed within its 0.35kg/MWhSO target.
Eskom said illegal connections and meter tampering still damage equipment and create safety risks in some areas. Because of this, it still uses load reduction in high-risk zones as a temporary measure.
The utility said seven of the country’s nine provinces are now free from load reduction. About 1.6 million customers who were affected have returned to normal supply.
Eskom said it is running a phased programme on 971 feeders across all provinces. The programme covers about 1.69 million of its 7.2 million customers.
The work includes smart meters, linking up Distributed Energy Resources and more Free Basic Electricity support. Eskom said customer education campaigns will run alongside these steps.
Eskom said its aim is to end load reduction completely by March 2027.
Source: this article is based on reporting by SAnews.gov.za. Image: GCIS via SAnews.gov.za. Written with the help of AI and published by the Tzaneen Voice Business desk. See our Editorial Standards.