NECSA Races Clock to Replace SAFARI-1 Reactor Before Its Licence Ends in 2030

By

November 22, 2026

Plans to replace the SAFARI-1 nuclear reactor at Pelindaba near Hartbeespoort have moved slowly, with its operating licence due to expire in 2030, MyBroadband reported.

Cabinet approved the replacement of the ageing 20MW reactor more than five years ago. Little has happened since then to turn plans for a new multi-purpose reactor into reality.

NECSA chief executive Loyiso Tyabashe told Reuters that South Africa should not risk leaving a gap in the market for another supplier. “Once customers are gone, they are gone,” he said.

The Nuclear Energy Corporation of South Africa (NECSA) runs the Pelindaba Nuclear Research Centre. It first planned to start building the new reactor in March 2025.

Feasibility studies were only fully completed in the 2024/25 financial year. Building work is likely still many years away, according to the report.

NECSA has only now issued a tender for geotechnical and geophysical surveys of a possible site. That tender closes on 2 December 2026.

A second tender, for a seismic hazard assessment of the proposed site, is open for bids until 9 December 2026. The planned closing date for the main building contract is 15 May 2027.

NECSA said the licence of SAFARI-1 can be extended past 2030. This would depend on engineering checks, work to manage the reactor’s age and inspections while it runs.

An International Atomic Energy Agency (IAEA) inspection in February 2026 found the reactor was working well. The agency advised NECSA to strengthen how it manages the reactor’s age.

The IAEA plans a follow-up visit in 2028. The outcome will help decide what happens to the reactor.

SAFARI-1 does not make electricity, unlike the two reactors at Koeberg Power Station. It is a research reactor whose main job is producing medical isotopes.

These include molybdenum-99, iodine-131 and lutetium-177. NTP Radioisotopes, a NECSA subsidiary, handles this work.

Molybdenum-99 is used to make technetium-99m. Each year, it is used in tens of millions of scans for cancer, heart disease and other conditions.

According to the IAEA, SAFARI-1 produces about 20% of the world’s molybdenum-99. NTP Radioisotopes said the figure is closer to a third of global supply.

The reactor is also used to study materials and inspect parts. It serves as a training ground for South Africa’s nuclear scientists and engineers.

NECSA has raised concern about the delays. It pointed in particular to waiting for National Treasury approval to go out to tender.

A draft Basic Assessment Report for the new reactor warned about the risk of delay. It said South Africa could lose its ability to keep up isotope production and nuclear research.

Tyabashe said NECSA wanted the shutdown of SAFARI-1 and the start of the new reactor to happen side by side.

SAFARI stands for South African Fundamental Atomic Research Installation. It became the first nuclear reactor to go online in Africa on 18 March 1965.

Source: this article is based on reporting by MyBroadband. Image: MyBroadband. Written with the help of AI and published by the Tzaneen Voice Business desk. See our Editorial Standards.