Renewable energy developer Mulilo has reached financial close on its 77MW Leeuwpoort battery storage project near Carletonville in Gauteng, IOL Business Report said.
Absa, Nedbank and Standard Bank are among the lenders backing the project. The battery system will be able to store 308 megawatt hours of power.
Mulilo chief executive Jan Fourie said the project would help strengthen the country’s electricity system. “Projects such as Leeuwpoort play a critical role in enhancing grid stability, unlocking network capacity, and improving energy security,” Fourie said.
The project is in the Merafong City Local Municipality. It will link to the national grid through the Midas Main Transmission Substation.
It will supply storage and support services under a 15-year power purchase agreement. The buyer is the National Transmission Company South Africa, known as NTCSA.
Mulilo said its shareholders, Copenhagen Infrastructure Partners and Norfund, also backed the deal. Its partner Reatile Group was part of the deal as well.
The company has not shared the total cost of the project. It also did not say how much each bank has lent.
Fourie said that, with support from the government, the company was proud to deliver lasting value for the country. He said it would also create economic chances for local communities.
Mulilo said a local community trust would be part of the project. The company said the trust would give the community a long-term share in the benefits.
Reatile Group chief commercial officer Sunette Smith said the partnership was an investment in the country’s energy security. “Reatile Group is proud to partner on Leeuwpoort,” Smith said.
BYD Energy Storage will supply the battery system. Mulilo will manage the building work, operations and upkeep for the life of the project.
Leeuwpoort is the third Mulilo battery project to reach financial close in 2026. The first two were its Mercury and Hartbeesfontein projects.
The project won its place in Bid Window 2 of the Battery Energy Storage Independent Power Producer Procurement Programme. This government programme buys battery storage for the national grid.
According to a quarterly report from the Department of Electricity and Energy, eight preferred bidders were picked in Bid Window 2. Together they offer 615MW of storage.
In October, Electricity and Energy Minister Kgosientsho Ramokgopa confirmed a plan that puts 4,600MW of battery storage first. The plan also includes 5,000MW of gas power under the Integrated Resource Plan 2025.
The International Energy Agency has also said large battery storage can help South Africa keep the grid stable. It said batteries help the grid use more wind and solar power.
Financial close means the project’s agreements and funding are now final. It does not mean the facility is running yet. Mulilo has not given dates for building or switching on the plant.
Source: this article is based on reporting by IOL Business Report. Image: IOL Business Report. Written with the help of AI and published by the Tzaneen Voice Business desk. See our Editorial Standards.
Anelisa Nkuna covers business and money news for Tzaneen Voice. Anelisa reports on the rand, fuel prices, interest rates, jobs, Eskom, Transnet, farming and company results. The aim is simple: explain what the numbers mean for household budgets, small businesses and workers in South Africa.